Corus Colours at Shotton are
responsible for the manufacture of the Colourcoat ® range of pre-finished
steel products that are primarily used in the construction industries.
During the dismantling of a redundant production line an incident occurred
which resulted in a fire.
The fire created extensive heavy smoke and soot damage to the structure and
content of an adjoining building and production line comprised of four
sections each measuring 450 metres in length by 35 metres wide by 20 metres
high.

Rope Access Solutions - Case Studies
Client: Corus Colours
Location: Shotton, Deeside
Incident: Smoke Contamination
Because of the complicated coating processes employed by Corus that require
dust free surfaces and the big demand for the product BELFOR were instructed
to urgently decontaminate the full structure of the building and all the
services.
Due to the complexity of the building services layout and the limitations on
floor access the decontamination was carried out using a variety of working
at height techniques. These included mobile elevated work platforms (cherry
pickers, scissor lifts etc), scaffold towers and scaffolding. It was
realised that a combination of these access methods allowed the
decontamination to be carried out to the majority of the structure however
approximately 10% of the contaminated surfaces were deemed inaccessible with
‘traditional’ access techniques.
After intensive discussions BELFOR convinced Corus engineers that utilising rope access techniques was a viable option to decontaminate the ‘inaccessible’ areas in terms of health and safety, price and most importantly time. A programme of work was drawn up and all the relevant health and safety documentation was compiled. Using industry approved climbing techniques operatives were able to manoeuvre around the roof structure and access all remaining areas of the structure and services. The Corus engineers were so impressed with the ability and technical know-how of the rope access team they approved additional works beyond the initial work scope including advice on internal working at height issues and production line maintenance.
Paul
Bates: Production Manager, Corus Colours,
"This was a very difficult job, and BELFOR were professional and self
motivated and rope access was a quick and efficient solutions package."
"There were areas of the job where it was not possible to erect scaffolding
and so rope access was the solution provided and all in all hundreds of
thousands of pounds was saved in time and material costs (i.e. scaffolding)"
"BELFOR Were pro-active and demonstrated good knowledge, experience,
guidance and reassurance" "it is vital to 'Corus colours' that all surfaces
are clean in order for the application process and BELFOR fulfilled those
standards as well as the high health and safety standards set"
Paul was so impressed with the work BELFOR did during this job he has asked
us back to do some general decontamination work in the factory in difficult
to access places.