
Seabank Power Station is an 1145MW gas fired combined cycle power station jointly operated by British Gas and Scottish – Southern Electricity. On June 15th 2005 during normal operation the steam turbine suffered a catastrophic turbine blade failure.

Rope Access Solutions - Case Studies
Client: Seabank Power Ltd
Location: Hallern, Bristol
Incident: Smoke Contamination
The blade, rotating close to the speed
of sound; detached itself from the shaft and flew, like a missile, into one
of the adjacent steam corridors, ricocheting around inside severing pipe
work. The loss of the blade caused an immediate imbalance in the turbine,
causing it to jolt which in turn caused shaft bearing lubrication pipes to
be come detached pumping out oil under pressure. Unfortunately the released
oil quickly ignited and within a short space of time a severe fire developed
spreading under the turbine through the bunded pits on either side. The
turbine hall was immediately evacuated. The fire was largely contained
within the turbine enclosure and thermal damage was restricted to the
immediate vicinity however smoke logging was extensive and heavy throughout
the entire steam turbine hall and even extended into the adjacent gas
turbine hall.
BELFOR were called in on June 16th
and soon established that the entire building envelope, all services and
machinery/equipment contained inside would require decontamination. The main
problem to contend with during the decontamination were identified as the
height of the building (33 metres at the roof) and the highly ‘congested’
nature if all of the steam and water pipes, electrical cable trays and air
extraction ductwork. Discussions with the management of Seabank Power
determined that all decontamination work would have to be carried out
during a six week time window whilst the steam turbine was away for repair.
The three factors of height, congestion and time window meant that
‘alternative’ access solutions would have to be employed. The problem of the
roof height was overcome by the erection of a sophisticated hanging scaffold
platform built at a height of 28 metres. This left the problem of
decontaminating the walls and pipework/ductwork exteriors. This is where our
specialist rope access team were brought into action. After two weeks
planning and preparing health and safety documentation and work protocols
and 8 man rope access team assembled on site and over the next 6 weeks
decontaminate all the walls, high level ductwork/pipework and assisted in
decontaminating low level services and surfaces inaccessible by any other
means. Without this resource not only would BELFOR not have been able to
complete the work on time but also the costs would have been dramatically
higher as ‘traditional’ scaffolding would have been required.
When asked about BELFOR’s performance on site and the use of rope access in
particular Nick Ashby, Maintenance and Production Manager at Seabank
Power Station replied that “he has been very happy with the job” and “the
job was well executed, managed and supervised and health and safety was
good’. He went on to say that “the delivery was excellent and
rope access provided an appropriate solution to the problem”